[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134150":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134150,796,1,"单选题","推土机开挖土质路堑作业中，影响推土机作业效率的两个主要因素是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","切土和卸土",false,{"key":16,"text":17,"correct":18},"B","切土和运土",true,{"key":20,"text":21,"correct":14},"C","运土和折返",{"key":23,"text":24,"correct":14},"D","卸土与折返","2020 \u002F 2019版教材P3 推土机开挖土方作业由切土、运土、卸土、倒退，（或折返）、空回等过程组成一个循环。影响作业效率的主要因素是切土和运土两个环节，因此必须以最短的时间和距离切满土，并尽可能减少土在推运过程中散失。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]