[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134134,796,1,"单选题","软土地基处理施工时，采用塑料排水板施工的，机具就位的前一道工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","摊铺下层砂垫层",true,{"key":16,"text":17,"correct":18},"B","塑料排水板穿靴",false,{"key":20,"text":21,"correct":18},"C","机具移位",{"key":23,"text":24,"correct":18},"D","插入套管","2020版教材P21\u002F2019版教材P20 塑料排水板施工工艺程序：整平原地面→摊铺下层砂垫层→机具就位→塑料排水板穿靴一插入套管一拔出套管→割断塑料排水板→机具移位→摊铺上层砂垫层。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]