[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134132":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1134132,796,1,"单选题","抛石挤淤施工时,在抛石高出水面后,应采用重型机具碾压紧密,然后在其上设（ ）,再行填土压实。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","透水层",false,{"key":16,"text":17,"correct":14},"B","垫层",{"key":19,"text":20,"correct":21},"C","反滤层",true,{"key":23,"text":24,"correct":14},"D","封层","2020版教材P20\u002F2019版教材P19 5）抛石挤淤施工规定⑴当下卧地层平坦时，应沿道路中线向前呈三角形抛填，再渐次向两旁展开，将淤泥挤向两侧。（2）当下卧地层具有明显横向坡度时，应从下卧层高的一侧向低的一侧扩展，并在低侧边部多抛投不少于2m宽，形成平台顶面。⑶在抛石高出水面后，应采用重型机具碾压紧密，然后在其上设反滤层，再填土压实。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]