[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134128":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1134128,796,1,"单选题","可在冬期进行路基施工的工程项目是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","一级公路的土路基开挖",false,{"key":16,"text":17,"correct":14},"B","挖掘填方地段的台阶",{"key":19,"text":20,"correct":21},"C","岩石地段的路堑开挖",true,{"key":23,"text":24,"correct":14},"D","整修路基边坡","2020版教材P15\u002F2019版教材P14 是路基施工可冬期进行的工程项目1．泥沼地带河湖冻结到一定深度后，如需换土时可趁冻结期挖去原地面的软土、淤泥层换填合格的其他填料。2．含水量高的流动土质、流沙地段的路堑可利用冻结期开挖。3.河滩地段可利用冬期水位低，开挖基坑修建防护工程，但应采取加温保温措施，注意养护。4．岩石地段的路堑或半填半挖地段，可进行开挖作业。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]