[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134126":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134126,796,1,"单选题","滑坡防治的工程措施主要有（ ）、力学平衡以及改变滑带土三类。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","护面",false,{"key":16,"text":17,"correct":18},"B","排水",true,{"key":20,"text":21,"correct":14},"C","植树",{"key":23,"text":24,"correct":14},"D","注浆","2020版教材P33\u002F2019版教材P30 滑坡防治的工程措施：滑坡防治的工程措施主要有排水、力学平衡和改变滑带土三类。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]