[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134121":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134121,796,1,"单选题","袋装砂井处理软基的工艺流程中，“沉入砂袋”的后一道工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拔出套管",true,{"key":16,"text":17,"correct":18},"B","机具定位",false,{"key":20,"text":21,"correct":18},"C","埋砂袋头",{"key":23,"text":24,"correct":18},"D","摊铺下层砂垫层","2020版教材P21\u002F2019版教材P20 袋装砂井施工工艺程序：整平原地面一摊铺下层砂垫层一机具定位一打入套管一沉入砂袋一拔出套管一机具移位一埋砂袋头一摊铺上层砂垫层。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]