[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134108":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134108,796,1,"单选题","下列路基工程可安排冬期施工的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","岩石地段的路堑开挖",true,{"key":16,"text":17,"correct":18},"B","在河滩低洼地带将被水淹的填土路堤",false,{"key":20,"text":21,"correct":18},"C","填方路基原地面草皮的铲除",{"key":23,"text":24,"correct":18},"D","高速公路的土路堤填筑。","2020版教材P15\u002F2019版教材P14 在反复冻融地区，昼夜平均温度在-3℃以下，连续10d以上时，进行路基施工称为路基冬期施工。当昼夜平均温度虽然上升到-3℃以上，但冻土未完全融化时，亦应按冬期施工。（1）路基工程可冬期进行的项目①泥沼地带河湖冻结到一定深度后，如需换土时可趁冻结期挖去原地面的软土、淤泥层换填合格的其他填料。②含水量高的流动土质、流沙地段的路堑可利用冻结期开挖。③河滩地段可利用冬季水位低，开挖基坑修建防护工程，但应采取加温保温措施，注意养护。④岩石地段的路堑或半填半挖地段，可进行开挖作业。（2）路基工程不宜冬期施工的项目①高速公路、一级公路的土路基和地质不良地区的二级以下公路路堤。②铲除原地面的草皮、挖掘填方地段的台阶。③整修路基边坡。④在河滩低洼地带将被水淹的填土路堤。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]