[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134106":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134106,796,1,"单选题","下列关于软基处理粒料桩施工方法的叙述，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按整平地面→振冲器就位对中→成孔→清孔→加料振密→关机停水→振冲器移位的施工工艺程序进行",false,{"key":16,"text":17,"correct":18},"B","应配备适用的供水设备，出口水压应为400～600kPa，流量20～40m3\u002Fh",true,{"key":20,"text":21,"correct":14},"C","选择振冲器型号应与桩径、桩长及加固工程离周围建筑物距离相适应",{"key":23,"text":24,"correct":14},"D","起重机械起吊能力应大于100～200kN","2020版教材P22\u002F2019版教材P21 出口水压应为400~600kPa，流量20~30m3／h。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]