[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1134064,796,1,"单选题","隧道施工预支护技术中，（ ）主要适用于围岩压力来得快、来得大，用于对围岩变形及地表下沉有较严格限制要求的软弱破碎围岩隧道工程中。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","超前锚杆",false,{"key":16,"text":17,"correct":14},"B","预注浆加固",{"key":19,"text":20,"correct":21},"C","管棚",true,{"key":23,"text":24,"correct":14},"D","超前小导管","2020版教材P240\u002F2019版教材P234 管棚主要适用于围岩压力来得快、来得大，用于对围岩变形及地表下沉有较严格限制要求的软弱破碎围岩隧道工程中",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]