[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134061":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134061,796,1,"单选题","隧道施工在辅以大型机具设备时宜采用（ ）施工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","台阶开挖法",false,{"key":16,"text":17,"correct":18},"B","全断面开挖法",true,{"key":20,"text":21,"correct":14},"C","分部开挖法",{"key":23,"text":24,"correct":14},"D","隧道挖掘机法","2020版教材P242\u002F2019版教材P237 在全断面开挖成形或大断面开挖成形的隧道衬砌施工中，则应尽量使用金属模板台车灌注混凝土整体衬砌。反过来可得出有了大型机具设备时采用全断面开挖",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]