[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134059,796,1,"单选题","山岭隧道复合式衬砌中防水层的施工时间应在（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","初期支护变形基本稳定前",false,{"key":16,"text":17,"correct":14},"B","二次衬砌施工作业后",{"key":19,"text":20,"correct":14},"C","初期支护变形和二次衬砌施工期间",{"key":22,"text":23,"correct":24},"D","初期支护变形基本稳定后，二次衬砌施工前",true,"2020版教材P244\u002F2019版教材P238 二次模筑混凝土衬砌的施工，应根据监控量测结果，在围岩和初期支护变形基本稳定后进行。当围岩变形较大，流变特性明显时，应加强初期支护或采用其他辅助工程措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]