[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134054":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1134054,796,1,"单选题","涌水段施工采用辅助坑道排水时，坑道应超前正洞（ ）m。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1～5",false,{"key":16,"text":17,"correct":14},"B","5～8",{"key":19,"text":20,"correct":21},"C","10～20",true,{"key":23,"text":24,"correct":14},"D","30～40","2020版教材P255\u002F2019版教材P249 二、采用辅助坑道排水时应符合的要求1.坑道应和正洞平行或接近平行。2.坑道底标高应低于正洞底标高。3.坑道应超前正洞10~20m,至少应超前1~2个循环进尺。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]