[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134051":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134051,796,1,"单选题","复合式衬砌隧道和喷锚衬砌隧道施工时的现场监控量测的必测项目是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","围岩体内位移（洞内设点）",false,{"key":16,"text":17,"correct":14},"B","围岩体内位移（地表设点）",{"key":19,"text":20,"correct":14},"C","围岩压力",{"key":22,"text":23,"correct":24},"D","拱顶下沉",true,"2020版教材P231\u002F2019版教材P225 表1B414022-1也有提到。根据《公路隧道施工技术规范》的规定，复合式衬砌隧道和喷锚衬砌隧道施工时必须进行的必测项目有洞内外观察、周边位移、拱顶下沉、地表下沉4个，其余的为选测项目。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]