[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134039":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134039,796,1,"单选题","在隧道施工监控量测中，收敛计用来测量（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","拱顶下沉",false,{"key":16,"text":17,"correct":14},"B","地表下沉",{"key":19,"text":20,"correct":14},"C","围岩体内位移",{"key":22,"text":23,"correct":24},"D","围岩周边位移",true,"2020版教材P231\u002F2019版教材P225 在复合式衬砌和喷锚衬砌隧道施工时必须进行必测项目的量测。必测项目见表1B414022-1。应根据设计要求、隧道横断面形状和断面大小、埋深、围岩条件、周边环境条件、支护类型和参数、施工方法等综合选择选择项目。选择项目见表B414022-2。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]