[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134031,796,1,"单选题","复合式衬砌的隧道地质和支护状况观察量测的间隔时间是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3次\u002Fd",false,{"key":16,"text":17,"correct":14},"B","2次\u002Fd",{"key":19,"text":20,"correct":14},"C","1～2次\u002Fd",{"key":22,"text":23,"correct":24},"D","每次爆破后进行",true,"2020版教材P232\u002F2019版教材P226 2。爆破开挖后应立即进行工程地质与水文地质状况的观察和记录，并进行地质描述。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]