[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134013":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134013,796,1,"单选题","某隧道是Ⅳ～Ⅴ级围岩其覆盖层厚度为80—250m。有关隧道量测内容和方法论述错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该隧道开挖后应及时进行围岩、初期支护的周边位移量测、拱顶下沉量测",false,{"key":16,"text":17,"correct":14},"B","该隧道初期支护完成后应进行喷层表面的观察和记录，并进行裂缝描述",{"key":19,"text":20,"correct":14},"C","该隧道如果围岩差、断面大或地表沉降控制严格时，宜进行围岩体内位移量测和其他量测",{"key":22,"text":23,"correct":24},"D","该隧道全线应进行地表沉降量测",true,"2020版教材P232\u002F2019版教材P226 位于Ⅳ-Ⅵ级围岩中且覆盖层厚度小于4 0 m的隧道，应进行地表沉降量测。本试题是Ⅳ-Ⅴ级围岩中且覆盖层厚度为80-250m。所以不用进行地表沉降量测。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]