[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133992":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133992,796,1,"单选题","二次衬砌的施作应在已产生的各项位移已达预计总位移量的（ ）后进行。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10%～20%",false,{"key":16,"text":17,"correct":14},"B","30%～40%",{"key":19,"text":20,"correct":14},"C","50%～60%",{"key":22,"text":23,"correct":24},"D","＞90%",true,"2020版教材P232\u002F2019版教材P227 5.二次衬砌的施作应在满足下列要求时进行： （1）隧道水平净空变化速度及拱顶或底板垂直位移速度明显下降； （2）隧道位移相对值已达到相对位移量的90%以上。 对浅埋、软弱、高地应力围岩等特殊地段应视现场情况确定。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]