[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133767":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133767,796,1,"单选题","监理人在收到承包人进度付款申请单以及相应的支持性证明文件后的（ ）d内完成核查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","28","2020版教材P398\u002F2019版教材P390 监理人在收到承包人进度付款申请单以及相应的支持性证明文件后的14d内完成核查",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]