[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133765,796,1,"单选题","竣工后一次结算的方法适用的建筑安装工程是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期小于1年或合同价值小于100万元",true,{"key":16,"text":17,"correct":18},"B","工期小于1年或合同价格大于100万元",false,{"key":20,"text":21,"correct":18},"C","工期大于1年或合同价格小于100万元",{"key":23,"text":24,"correct":18},"D","工期大于1年或合同价格大于100万元","2020版教材P398\u002F2019版教材P390 竣工后一次结算。建设项目或单项工程全部建筑安装工程建设期在12个月以内，或者工程承包价值在100万元以下的，可以实行工程价款每月月中预支，竣工后一次结算。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]