[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133763":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133763,796,1,"单选题","开工预付款支付的条件有：一是承包人和发包人已签订了施工合同，二是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人已提交了开工预付款保函",true,{"key":16,"text":17,"correct":18},"B","材料、设备符合规范要求并经监理工程师认可",false,{"key":20,"text":21,"correct":18},"C","承包人已出具材料、设备费用凭证或支付单据",{"key":23,"text":24,"correct":18},"D","承包人的施工队伍已进场","2020版教材P402\u002F2019版教材P394 开工预付款支付的条件有：（1）承包人和发包人已签订了施工合同；（2）承包人已提交了开工预付款保函。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]