[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133751,796,1,"单选题","成本计划的核心是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全面成本管理",false,{"key":16,"text":17,"correct":18},"B","确定责任目标成本",true,{"key":20,"text":21,"correct":14},"C","科学管理成本",{"key":23,"text":24,"correct":14},"D","有效管理成本","2020版教材P378\u002F2019版教材P370 编制施工成本计划的关键是确定贵任目标成本，这是成本计划的核心，是成本管理所要达到的目标，成本目标通常以项目成本总降低额和降低率来定量地表示。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]