[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133749":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133749,796,1,"单选题","（ ）作为现场施工成本控制的目标。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","现场施工成本偏差",false,{"key":16,"text":17,"correct":14},"B","现场施工成本降低额",{"key":19,"text":20,"correct":21},"C","现场施工计划成本",true,{"key":23,"text":24,"correct":14},"D","现场施工成本降低率","2020版教材P378\u002F2019版教材P370 当计划预控偏差总和为正值时，应进一步改善施工方案，寻找有潜力的分部分项工程，挖掘降低施工预算成本的途径和措施，保证现场计划总成本控制在责任目标总成本的范围内。通过以上施工预算成本的计算与平衡之后，形成的现场施工计划成本，作为现场施工成本控制的目标。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]