[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133745":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133745,796,1,"单选题","施工计划成本偏差正值是表示（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度超前",false,{"key":16,"text":17,"correct":18},"B","计划预控不到位",true,{"key":20,"text":21,"correct":14},"C","进度拖延",{"key":23,"text":24,"correct":14},"D","计划预控到位","2020版教材P378\u002F2019版教材P370 将各项施工预算成本与相应项的责任目标成本进行比较，计算其计划成本偏差。现场计划成本偏差是指现场施工预算成本与责任目标成本之差，即：计划成本偏差=施工预算成本-责任目标成本。计划成本偏差反映现场施工成本在计划阶段的预控情况，也称施工成本计划预控偏差。正值表示计划预控不到位，不满足该项责任目标成本的要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]