[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133744":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133744,796,1,"单选题","下列有关工程成本控制的说法中错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应以施工预算控制成本支出",false,{"key":16,"text":17,"correct":18},"B","应在项目成本计划的基础上编制成本预测",true,{"key":20,"text":21,"correct":14},"C","应建立资源消耗台账实行资源消耗的中间控制",{"key":23,"text":24,"correct":14},"D","应加强质量管理控制质量成本","2020版教材P377\u002F2019版教材P370 该题主要考察的是：公路工程施工成本控制公路项目施工成本计划的编制工程项目成本计划的编制过程，实际上也是工程成本的事前预控过程。一、确定责任目标成本编制施工成本计划的关键是确定责任目标成本，这是成本计划的核心，是成本管理所要达到的目标，成本目标通常以项目成本总降低额和降低率来定量地表示。在工程项目的施工过程中，每月应根据施工进度计划，编制材料需用量计划，建立材料消耗台账，如超出限额领料，要分析原因，及时采取纠正措施.B选项应该是“在成本预测的基础上编制成本计划”",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]