[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133742,796,1,"单选题","下列属于施工中材料费的控制措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","控制购买价",false,{"key":16,"text":17,"correct":14},"B","节省运费",{"key":19,"text":20,"correct":21},"C","限额领料",true,{"key":23,"text":24,"correct":14},"D","减少包装","2020版教材P383\u002F2019版教材P375 对材料成本控制，一是要以预算价格来控制材料的采购成本。二是对材料的数量控制，在工程项目的施工过程中，每月应根据施工进度计划，编制材料需用量计划，建立材料消耗台账，如超出限额领料，要分析原因，及时采取纠正措施；同时通过实行“限额领料”来控制材料领用数量，并控制工序施工质量，争取一次合格，避免因返工而增加材料损耗。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]