[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133713":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133713,796,1,"单选题","在合同履行过程中，经发包人同意，监理人可按合同条款约定的变更程序向承包人作出变更指示，承包人的做法错误的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","经检查认为其中存在合同约定变更情形的，可向监理工程师提出书面变更协议",false,{"key":16,"text":17,"correct":14},"B","认为难以实施此项变更，应立即通知监理工程师，对其说明原因并附详细依据",{"key":19,"text":20,"correct":14},"C","认为可以实施的，立即着手实施",{"key":22,"text":23,"correct":24},"D","认为难以实施此项变更的，应立即无理由拒绝",true,"2020版教材P369\u002F2019版教材P362 承包人在收到监理工程师按合同约定发出的图纸和文件，经检查认为其中存在合同约定变更情形的，可向监理工程师提出书面变更协议。认为难以实施此项变更，应立即通知监理工程师，对其说明原因并附详细依据，监理工程师与发包人协商后确定撤销改变或不改变原更更意向书",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]