[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133711,796,1,"单选题","施工中，监理工程师在收到承包人书面建议后，应与发包人共同研究，确认存在变更的，应在收到承包人书面建议后的（ ）d内作出变更指示。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","16",{"key":23,"text":24,"correct":14},"D","20","2020版教材P369\u002F2019版教材P362 监理工程师在收到承包人书面建议后，应与发包人共同研究，确认存在变更的，应在收到承包人书面建议后的14d内作出变更指示。经研究后不同意作为变更的，应由监理工程师书面答复承包人。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]