[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133707,796,1,"单选题","按照（ ）划分，工期延误分为单一性延误和共同延误。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","延误索赔结果",false,{"key":16,"text":17,"correct":14},"B","延误的原因",{"key":19,"text":20,"correct":14},"C","延误是否处于关键路线上",{"key":22,"text":23,"correct":24},"D","延误发生的时间",true,"2020版教材P373\u002F2019版教材P365 按照延误发生的时间划分，工期延误分为单一性延误和共同延误。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]