[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133648,796,1,"单选题","施工中需要控制预拱度的桥梁是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","简支梁桥",true,{"key":16,"text":17,"correct":18},"B","斜拉桥",false,{"key":20,"text":21,"correct":18},"C","拱桥",{"key":23,"text":24,"correct":18},"D","悬索桥","2020版教材P324\u002F2019版教材P318 桥梁上部结构施工中常见质量控制关键点（1）简支梁桥①简支梁混凝土的强度控制。②预拱度的控制。③支座预埋件的位置控制。④大梁安装时梁与梁之间髙差控制。⑤支座安装型号、方向的控制。⑥梁板之间现浇带混凝土质量控制。⑦伸缩缝安装质量控制。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]