[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133617,796,1,"单选题","以时间为纵轴的公路工程进度计划的形式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图",false,{"key":16,"text":17,"correct":14},"B","“S”曲线",{"key":19,"text":20,"correct":14},"C","斜率图",{"key":22,"text":23,"correct":24},"D","斜条图",true,"2020版教材P299\u002F2019版教材P293 垂直图（也称斜条图、时间里程图）。垂直图是以公路里程或工程位置为横轴，以时间为纵轴，而各分部（项）工程的施工进度则相应地以不同的斜线表示。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]