[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133614,796,1,"单选题","下列公路工程进度计划的主要形式中，以累计完成的工程量的百分数为纵轴的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","网络图",false,{"key":16,"text":17,"correct":14},"B","垂直图",{"key":19,"text":20,"correct":21},"C","斜率图",true,{"key":23,"text":24,"correct":14},"D","“S”曲线","2020版教材P299\u002F2019版教材P293 斜率图是以时间（月份）为横轴，以累计完成的工程量的百分数为纵轴，将分项工程的施工进度相应地用不同斜率表示的图表化曲（折）线。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]