[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133606":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133606,796,1,"单选题","考虑沥青路面结构层持续时间时，不属于影响因素的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","沥青拌合机的能力",false,{"key":16,"text":17,"correct":14},"B","摊铺速度",{"key":19,"text":20,"correct":14},"C","混合料的出厂温度",{"key":22,"text":23,"correct":24},"D","开放交通的温度",true,"2020版教材P301\u002F2019版教材P295 各结构层的施工速度和持续时间。要考虑影响每个施工段的因素，水泥稳定碎石的延迟时间、沥青拌和能力、温度要求、摊铺速度、养护时间、最小工作面的要求等。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]