[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133604":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133604,796,1,"单选题","在对进度计划进行工期和时间安排的合理性审查时，应重点审查（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工总工期的安排应符合合同工期",true,{"key":16,"text":17,"correct":18},"B","主要骨干人员及施工队伍的进场日期已经落实",false,{"key":20,"text":21,"correct":18},"C","各项施工方案和施工方法应与施工经验和技术水平相适应",{"key":23,"text":24,"correct":18},"D","所需主要材料和设备的运送日期已有保证","2020版教材P303\u002F2019版教材P297 工期和时间安排的合理性：1）施工总工期的安排应符合合同工期。2）各施工阶段或单位工程（包括分部、分项工程）的施工顺序和时间安排与材料和设备的进场计划相协调。3）易受冰冻、低温、炎热、雨季等气候影响的工程应安排在适宜的时间，并应采取有效的预防和保护措施。4）对动员、清场、假日及天气影响的时间，应充分考虑并留有余地。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]