[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133600":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133600,796,1,"单选题","在对进度计划进行计划目标与施工能力的适应性审查时，应重点审查（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工总工期的安排应符合合同工期",false,{"key":16,"text":17,"correct":14},"B","主要骨干人员及施工队伍的进场日期已经落实",{"key":19,"text":20,"correct":21},"C","各项施工方案和施工方法应与施工经验和技术水平相适应",true,{"key":23,"text":24,"correct":14},"D","所需主要材料和设备的运送日期已有保证","2020版教材P304\u002F2019版教材P298 计划目标与施工能力的适应性：（1）各阶段或单位工程计划完成的工程量及投资额应与设备和人力实际状况相适应。（2）各项施工方案和施工方法应与施工经验和技术水平相适应。（3）关键线路上的施工力量安排应与非关键线路上的施工力量安排相适应。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]