[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133590,796,1,"单选题","下列关于工程量清单的编写说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","清单说明主要说明在编制工程量清单时应遵守的规定及注意事项",false,{"key":16,"text":17,"correct":14},"B","不同种类的工作应分别列出项目",{"key":19,"text":20,"correct":14},"C","同一性质但施工部位或条件不同的工作应分别列出项目",{"key":22,"text":23,"correct":24},"D","劳务和施工机械两个计日工表的计量（或计价）单位是“日”",true,"2020版教材P289\u002F2019版教材P283 施工进度计划的编制。施工方法和土方调配决定以后，即可计算得出路基工程的施工方数，然后根据所采用的施工定额，求出劳动力的工日数和施工机械的台班数量。从这里可以看出劳务的计量单位是“工日”，机械计量单位是“台班”，",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]