[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133587":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133587,796,1,"单选题","路面工程施工中，相邻结构层之间的速度决定了相邻结构层之间的搭接类型，前道工序的速度慢于后道工序时选用（ ）搭接类型。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开始到开始",false,{"key":16,"text":17,"correct":14},"B","开始到完成",{"key":19,"text":20,"correct":14},"C","完成到开始",{"key":22,"text":23,"correct":24},"D","完成到完成",true,"2020版教材P290\u002F2019版教材P284 根据施工速度选择搭接类型[前道工序速度快于后道工序时选用开始到开始（STS）类型，否则用完成到完成（FTF）类型]，并根据各结构层施工速度和所需要的工作面大小计算出搭接时距，同时还要考虑到各结构层可能需要技术间歇时间的影响，以及路面各结构层的质量检验所需的时间等。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]