[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133583":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133583,796,1,"单选题","桥梁下部的桥墩流水施工的工序太多时，简化合并为墩与墩之间的关系，此时墩与墩之间的关系是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开始到完成",false,{"key":16,"text":17,"correct":14},"B","完成到开始",{"key":19,"text":20,"correct":21},"C","搭接关系",true,{"key":23,"text":24,"correct":14},"D","衔接关系","2020版教材P290\u002F2019版教材P285 桥梁下部的桥墩施工时，如果设备或者模板数量有限可采用流水施工方式组织施工。对于采用流水施工时应注意流水施工的相关时间参数：流水节拍、流水步距、技术间歇等。当很多个墩流水施工时，表示其流水关系显得工作（工序）太多和过于繁杂，如果采用以下两种简化表示，应注意原本各工作（工序）之间衔接的逻辑关系，经过简化成为墩与墩的关系时，墩与墩的逻辑关系就变成搭接关系；",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]