[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133527":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133527,796,1,"单选题","下列各项合同文件按照优先解释的原则，处于最后解释的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","中标通知书",false,{"key":16,"text":17,"correct":14},"B","专项合同条款",{"key":19,"text":20,"correct":14},"C","技术规范",{"key":22,"text":23,"correct":24},"D","图纸",true,"本题考查的是公路项目施工合同的履行与管理方法。合同文件的优先顺序：（1）合同协议书；（2）中标通知书；（3）投标函及投标函附录；（4）项目专用合同条款；（5）公路工程专用合同条款；（6）通用合同条款；（7）工程量清单计量规则；（8）技术规范；（9）图纸；（10）已标价工程量清单；（11）承包人有关人员、设备投入的承诺及投标文件中的施工组织设计；（12）其他合同文件。参见教材P357～358。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]