[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133514,796,1,"单选题","“前锋线比较法”主要适用于（）的进度计划检查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时标网络图",true,{"key":16,"text":17,"correct":18},"B","“S”型曲缝",false,{"key":20,"text":21,"correct":18},"C","横道图",{"key":23,"text":24,"correct":18},"D","“香蕉”型曲线","前锋线比较法是通过绘制某检查时刻工程项目实际进度前锋线，进行工程实际进度与计划进度比较的方法，它主要适用于时标网络计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]