[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133510,796,1,"单选题","下列关于土方路基工程施工中常见质量控制关键点的错误表达是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工放样与断面测量",false,{"key":16,"text":17,"correct":14},"B","分层压实，控制填土的含水量，确保压实度达到设计要求",{"key":19,"text":20,"correct":14},"C","路基原地面处理，按施工技术合同或规范规定要求处理，并认真整平压实",{"key":22,"text":23,"correct":24},"D","拌和设备计量装置校验",true,"本题考查的是公路工程质量控制的常用方法。土方路基工程施工中常见质量控制关键点：（1）施工放样与断面测量；（2）路基原地面处理，按施工技术合同或规范规定要求处理，并认真整平压实；（3）使用适宜材料，保证原材料合格，正确确定土的最大干密度和最佳含水量；（4）压实设备及压实方案；（5）路基纵横向排水系统设置；（6）每层的松铺厚度，横坡及填筑速率；（7）分层压实，控制填土的含水量，确保压实度达到设计要求。参见教材P315。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]