[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133492":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133492,796,1,"单选题","监理工程师已向承包人出具经发包人签认的进度付款证书，则发包人应在监理人收到进度付款申请单后的（ ）天内，将进度应付款支付给承包人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":18},"B","28",true,{"key":20,"text":21,"correct":14},"C","30",{"key":23,"text":24,"correct":14},"D","56","本题考查的是公路工程分包合同管理。发包人应在监理人收到进度付款申请单后的28天内，将进度应付款支付给承包人。参见教材P360。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]