[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133484":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133484,796,1,"单选题","下列计划中，不属于资源计划的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","劳动力计划",false,{"key":16,"text":17,"correct":18},"B","施工进度计划",true,{"key":20,"text":21,"correct":14},"C","材料计划",{"key":23,"text":24,"correct":14},"D","施工机械设备计划","各项资源需求计划根据已确定的施工进度计划，编制各项资源需求及进场计划，主要有: （1）劳动力需求计划。 （2）材料需求计划。 （3）施工机械设备需求计划。 （4）资金需求计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]