[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133478":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133478,796,1,"单选题","关于工程进度曲线（“S”曲线）特点的说法，错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一般情况下，项目施工初期的曲线斜率是逐渐增大的",false,{"key":16,"text":17,"correct":18},"B","一般情况下，项目施工后期的曲线为凹型",true,{"key":20,"text":21,"correct":14},"C","通过对“S”曲线的形状分析，可以定性分析施工组织设计中工作内容安排的合理性",{"key":23,"text":24,"correct":14},"D","在项目实施过程中，“S”曲线可结合工程进度管理曲线（“香蕉”曲线）进行施工进度、费用控制","项目施工后期，每天完成的工程量逐渐减少，施工投入也减少，此时施工速度也逐步放慢即工程进度曲线的斜率逐步减小，此阶段的曲线则为凸形。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]