[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133454":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133454,796,1,"单选题","下列测量工作中不属于开工准备阶段测量工作的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","交接桩",false,{"key":16,"text":17,"correct":14},"B","施工控制网建立",{"key":19,"text":20,"correct":14},"C","地形地貌复核测量",{"key":22,"text":23,"correct":24},"D","施工放样测量",true,"本题考查的是公路工程施工测量管理。开工准备阶段测量包括：交接桩、设计控制桩贯通复测、施工控制网建立、地形地貌复核测量。参见教材P308。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]