[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133417":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":13},1133417,796,1,"单选题","预应力后张法张拉施工时，工具锚（夹具）、千斤顶和工作锚（锚具）正确的安装顺序是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作锚——千斤顶——工具锚",true,{"key":16,"text":17,"correct":18},"B","工具锚——千斤顶——工作锚",false,{"key":20,"text":21,"correct":18},"C","工具锚——工作锚——千斤顶",{"key":23,"text":24,"correct":18},"D","工作锚——工具锚——千斤顶",{"id":6,"name":26,"category":27,"favorite":28},"一建公路工程实务","建筑工程",0]