[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133409":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133409,796,1,"单选题","移动支架逐孔现浇施工中，当一孔梁的混凝土浇筑施工完成后，内模中的侧向模板应在混凝土抗压强度达到（ ）后，顶面模板应在混凝土抗压强度达到设计强度的（ ）后，方可拆除。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5.0MPa，75%",false,{"key":16,"text":17,"correct":14},"B","2.5MPa，80%",{"key":19,"text":20,"correct":14},"C","5.0MPa，80%",{"key":22,"text":23,"correct":24},"D","2.5MPa，75%",true,"本题考查的是逐孔施工。一孔梁的混凝土浇筑施工完成后，内模中的侧向模板应在混凝土抗压强度达到2.5MPa后，顶面模板应在混凝土抗压强度达到设计强度的75%后，方可拆除；外模架应在梁体建立预应力后方可卸落。参见教材P175。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]