[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133377":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133377,796,1,"单选题","钻孔灌注桩施工中，钻孔至设计孔深后，其紧后工序是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","下放导管",false,{"key":16,"text":17,"correct":18},"B","清孔",true,{"key":20,"text":21,"correct":14},"C","钢筋笼制作及安放",{"key":23,"text":24,"correct":14},"D","灌注水下混凝土","钻孔灌注桩施工的主要工序有：埋设护筒、制备泥浆、钻孔、清底、钢筋笼制作与吊装以及灌注水下混凝土等。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]