[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133351":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133351,796,1,"单选题","悬索桥主缆施工的主要工序包括： ①主缆架设； ②猫道架设； ③索夹安装与吊索架设； ④紧缆； ⑤牵引系统施工。其正确的施工工序为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→③→④→⑤",false,{"key":16,"text":17,"correct":18},"B","⑤→②→①→④→③",true,{"key":20,"text":21,"correct":14},"C","②→⑤→④→①→③",{"key":23,"text":24,"correct":14},"D","⑤→③→①→④→②","本题考查的是悬索桥的主缆施工。主缆施工顺序：牵引系统→猫道→主缆架设→紧缆→索夹安装与吊索架设。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]