[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133325":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133325,796,1,"单选题","桥梁上部结构悬臂浇筑法施工中，为减少因温度变化而对合龙段混凝土产生拉应力，合龙段混凝土浇筑时间应安排在一天中的（）时段浇筑。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","平均气温",false,{"key":16,"text":17,"correct":14},"B","最高气温",{"key":19,"text":20,"correct":21},"C","最低气温",true,{"key":23,"text":24,"correct":14},"D","任意","本题考查的是悬臂浇筑施工。合龙前应在两端悬臂预加压重，并于浇筑混凝土过程中逐步撤除，使悬臂挠度保持稳定。合龙宜在一天中最低气温时完成，合龙段的混凝土强度等级可提高一级，以尽早张拉。合龙段混凝土浇筑完成后应加强养护，悬臂端应覆盖，防止日晒。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]