[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133323":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133323,796,1,"单选题","在预应力混凝土构件制作的后张法张拉施工中，对预应力筋张拉时，构件混凝土强度应符合设计要求；当设计无要求时，其强度应保证（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不应低于极限强度值的80％",false,{"key":16,"text":17,"correct":14},"B","不应低于标准强度值的80％",{"key":19,"text":20,"correct":14},"C","不应低于平均强度等级值的80％",{"key":22,"text":23,"correct":24},"D","不应低于设计强度等级值的80％",true,"本题考查的是后张法预制梁板。在预应力混凝土构件制作的后张法张拉施工中，对预应力筋张拉时，构件混凝土强度应符合设计要求；当设计无要求时，其强度应保证不应低于设计强度等级值的80％。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]